The Perception of Construction Industry Players on Drone Technology: Impact on Project Delays and Work Quality
Keywords:
Drone Technology, Construction Management, Project Delays, Work QualityAbstract
Introduction/Main Objectives: This study aimed to systematically investigate the perception of construction industry players regarding the effectiveness of drone technology in mitigating project delays and improving work quality on construction sites.
Background Problems: The global construction industry faces persistent challenges from project delays and work quality variations, leading to financial losses. Despite the growing adoption of drone technology as a monitoring solution, there is a lack of empirical evidence on how industry players themselves perceive its effectiveness in addressing these core issues.
Research Methods: A quantitative survey method was employed, targeting a sample of construction professionals (project managers, engineers, contractors) in Southern Malaysia. Data were analyzed using descriptive statistics to measure the intensity of industry perception.
Finding/Results: Results showed an overwhelmingly strong positive perception. The mean score for perceived effectiveness in reducing project delays was 4.26. The mean score for perceived impact on improving work quality was 4.26 (based on a 5-point Likert Scale).Familiarity and hands-on experience with drone technology led to more informed and nuanced evaluations of its benefits.
Conclusion: Construction industry players view drone technology as a highly valuable and effective intervention for enhancing both project timeliness and quality. The study provides critical, evidence-based justification for its strategic adoption, offering clear guidance to construction firms and policymakers on maximizing the technology's benefits to address key sector performance challenges.
References
Almusaiabi, H. and Naimi, S. (2023). Total quality management’s critical role in resolving delay issue of construction projects submission. Mathematical Modelling and Engineering Problems, 10(4), 1419-1426. https://doi.org/10.18280/mmep.100437
Alsamarraie, M., Ghazali, F., Hatem, Z., & Flaih, A. (2022). A review on the benefits, barriers of the drone employment in the construction site. Jurnal Teknologi, 84(2), 121-131. https://doi.org/10.11113/jurnalteknologi.v84.17503
Duarte-Vidal, L., Herrera, R., Atencio, E., & Rivera, F. (2021). Interoperability of digital tools for the monitoring and control of construction projects. Applied Sciences, 11(21), 10370. https://doi.org/10.3390/app112110370
Eiris, R., Zhou, S., & Gheisari, M. (2018). Integrating the use of uavs and photogrammetry into a construction management course: lessons learned. https://doi.org/10.22260/isarc2018/0061
Jacob-Loyola, N., Rivera, F., Herrera, R., & Atencio, E. (2021). Unmanned aerial vehicles (uavs) for physical progress monitoring of construction. Sensors, 21(12), 4227. https://doi.org/10.3390/s21124227
Kazaz, A., Ulubeyli, S., & Tuncbilekli, N. (2012). Causes of delays in construction projects in turkey. Journal of Civil Engineering and Management, 18(3), 426-435. https://doi.org/10.3846/13923730.2012.698913
Moskovchenko, D. and Mishuk, K. (2025). Integration of unmanned aerial vehicles into the construction process: comparison of traditional methods and modern technologies. Ways to Improve Construction Efficiency, 1(55), 3-12. https://doi.org/10.32347/2707-501x.2025.55(1).3-12
Mottaeva, A. (2024). Development strategies for unmanned aerial vehicles in the construction industry. E3S Web of Conferences, 515, 01020. https://doi.org/10.1051/e3sconf/202451501020
Namian, M., Khalid, M., Wang, G., & Türkan, Y. (2021). Revealing safety risks of unmanned aerial vehicles in construction. Transportation Research Record Journal of the Transportation Research Board, 2675(11), 334-347. https://doi.org/10.1177/03611981211017134
Ojeda, J., Huatangari, L., Calderón, B., Tineo, J., Panca, C., & Pino, M. (2024). Estimation of the physical progress of work using UAV and BIM in construction projects. Civil Engineering Journal, 10(2), 362-383. https://doi.org/10.28991/cej-2024-010-02-02
Sambasivan, M. and Soon, Y. (2007). Causes and effects of delays in malaysian construction industry. International Journal of Project Management, 25(5), 517-526. https://doi.org/10.1016/j.ijproman.2006.11.007
Sentosa, G., Agung, R., Marbun, C., Kurniawan, W., Ibady, A., Pierre, A., … & Insyira, A. (2023). Construction progress monitoring on toll road project using photogrammetry. Iop Conference Series Earth and Environmental Science, 1169(1), 012032. https://doi.org/10.1088/1755-1315/1169/1/012032
Sulbaran, T. (2023). Evaluating the comprehension of construction schedules of an artificial intelligence., 545-552. https://doi.org/10.36253/979-12-215-0289-3.53
Ullah, K., Khan, M., Lakhiar, M., Vighio, A., & Sohu, S. (2018). Ranking of effects of construction delay: evidence from Malaysian building projects. Journal of Applied Engineering Sciences, 8(1), 79-84. https://doi.org/10.2478/jaes-2018-0011
Yahya, M. Y., Shun, W. P., Yassin, A. M., & Omar, R. (2021). The challenges of drone application in the construction industry. Journal of Technology Management and Business, 8(1). https://doi.org/10.30880/jtmb.2021.08.01.003
Downloads
Published
How to Cite
Conference Proceedings Volume
Section
License
Copyright (c) 2026 Shahrun Nazida Salleh, Yuhani Jamian, Salsabilla Harisman